The challenge
Busway, cooling pipework and cable trays all needed space above the same aisles. The electrical installation had to leave access for other trades during the fit-out and for the facilities team to reach the tap-off units after the racks went in.
How the work was staged
The builder and services trades reviewed the shared routes and agreed the order of work by aisle. Supports and busway went in before the rack feeds. Tap-off positions were checked against the rack layout, and each feed was labelled to match the distribution schedule.
What was handed over
Completed aisles were recorded separately so the commissioning team could see which areas were ready for the next stage. The handover pack linked each area to its inspection records and noted any items still open.